1. Establish the current baseline
Name the approved specification, sample and artwork by their version numbers. Identify the orders and lots that use them. Ask the supplier to confirm who received that baseline.
2. Ask for a written change request
- Change: old requirement, proposed requirement and reason for change.
- Impact: cost, timing, affected lot, tests to repeat and any packaging or label changes.
- Decision: approver, approval date, files to replace and first lot using the new version.
3. Confirm receipt, then close the change
Share the approved revision with the supplier, inspector and any other assigned party. Keep the superseded file identifiable and record acknowledgement. Check early output from the new process against the approved change.